• NASA making fourth attempt to complete Artemis 1 Wet Dress Rehearsal

    From NasaSpaceFlight@1337:1/100 to All on Mon Jun 20 14:45:04 2022
    NASA making fourth attempt to complete Artemis 1 Wet Dress Rehearsal

    Date:
    Mon, 20 Jun 2022 13:39:07 +0000

    Description:
    NASA is counting down the fourth attempt at completing a practice launch day exercise with The post NASA making fourth attempt to complete Artemis 1 Wet Dress Rehearsal appeared first on NASASpaceFlight.com .

    FULL STORY ======================================================================

    NASA is counting down the fourth attempt at completing a practice launch day exercise with its Artemis 1 vehicle on the launch pad at the Kennedy Space Center (KSC) in Florida. The June 20 Wet Dress Rehearsal (WDR) test attempt
    is scheduled to culminate in two runs of the countdowns final ten minutes
    with the integrated Orion spacecraft and Space Launch System (SLS) rocket for Artemis 1 fully fueled and pressurized like it will be for launch.

    Following three attempts to complete the WDR countdown demonstration test in April, launch team members with the agencys Exploration Ground Systems (EGS) program and prime launch processing contractor Jacobs have fixed some hardware, updated some countdown software, and plan to fully fuel the two cryogenic stages on the SLS launch vehicle with liquid oxygen (LOX) and
    liquid hydrogen (LH2) before counting down to just a couple of seconds before ignition.

    If the test can be completed to NASAs satisfaction, the agency may soon have the data it needs to finally set an official launch date; currently, late August is the earliest that Artemis 1 could lift off.



    Ready to fuel SLS stages again for terminal countdown demonstration test

    The countdown timeline is again aligned to the same time of day as the first three attempts. For June 20, the simulated launch day for this attempt, the Mission Management Team (MMT) will hold their pre-tanking briefing early in the morning with a targeted, initial T-0 of 2:40 pm Eastern (18:40 UTC).

    On the planned schedule, the countdown would resume at T-10 minutes at 2:30
    pm Eastern (18:30 UTC), beginning the first of two terminal countdown runs conducted by the Ground Launch Sequencer (GLS) . The two terminal countdown runs would be planned within a two-hour long simulated launch window from
    2:40 pm to 4:40 pm Eastern (18:40 to 20:40 UTC), the same duration as the maximum amount of time NASA will have during eventual launch attempts for the Artemis 1 lunar mission . SLS on LC-39B for its wet dress rehearsal with the pads original 850,000 gallon liquid hydrogen storage sphere to the left. (Credit: Nathan Barker for NSF)

    The fourth attempt to complete this comprehensive test of vehicle and ground system countdown choreography comes after the vehicle was rolled out from
    KSCs Vehicle Assembly Building (VAB) to Launch Pad 39B for a second time on June 6 . Once the vehicle on its Mobile Launcher was lowered onto the pedestals at the pad by Crawler Transporter 2, a milestone also called hard down, ground teams began about two weeks of work to prepare for the WDR,
    which is the final, major, planned pre-launch test.

    Once we got hard down at the pad, we began what we call our pad validation
    and essentially what that does is it confirms our services and our connectivity between the pad and the ML and then back to the LCC, the Launch Control Center and our command-and-control system, Artemis 1 Launch Director Charlie Blackwell-Thompson, said in a June 15 media teleconference. That runs across several days and we finished up those validations and then the next
    big milestone for us was getting ready for the booster servicing.

    We performed that over this last weekend and so at this time we do have the hypergolic fuel load complete for the [Solid Rocket Booster (SRB)] hydraulic power units (HPU) that provides the booster thrust vector control (TVC)
    during flight and we do intend to test that system inside of the 30 second mark of our Wet Dress Rehearsal [countdown]. With pad validations and SRB hydraulic system servicing complete, teams in the Launch Control Center adjacent to the VAB and out at the launch pad with the vehicle began
    countdown preparations for the WDR. The Tail Service Masts which will fuel
    the Core Stage will LH2 and liquid oxygen. Seen here, the LH2 mast is visible with th e LOX mast perfectly hidden behind it. Both commodity TSMs connect to the same side of the Core State. (Credit: Nathan Barker for NSF L2)

    Call to stations for the test occurred at 5 pm Eastern (21:00 UTC) on June
    18, with the countdown clock starting 30 minutes later at T-43 hours, 10 minutes, and counting. Plans called for the clock to continue down to a 90-minute long hold at T-6 hours and 40 minutes for the pre-tanking decision point in the process.

    The hold should begin at 6 am Eastern (10:00 UTC) on June 20, concurrent with the MMT pre-tanking briefing. Then, if the MMT gives a go to tank the
    vehicle, propellant loading would begin to flow from storage spheres in the Pad 39B infield towards the rocket sometime between 7 am and 7:30 am Eastern, when the countdown would resume.

    The Artemis 1 Orion/SLS Block 1 Crew vehicle was originally rolled to Pad 39B in mid-March to complete a set of engineering tests followed by the WDR. A series of issues, some of which repeated themselves persistently, stopped the first three attempts in early and mid-April.

    The first attempt on April 3 was scrubbed before the fueling process began when supply fans located inside the Pad 39B area away from the Mobile
    Launcher stopped working. The second attempt was made the next day on the morning of April 4, but fueling was delayed for hours when the gaseous nitrogen (GN2) purge flow died.

    A high-flow rate of GN2 needed for SLS is drawn from the space center
    nitrogen gas supplier Air Liquide; after the plant was able to re-establish the flow of gas to inert areas inside the rocket, the launch team was able to begin loading liquid oxygen into the Core Stage after a false start or two. Credit: Julia Bergeron for NSF.

    The April 4 attempt was scrubbed when the team began preparations to begin loading liquid hydrogen into the vehicle and it was discovered that a panel
    on the Mobile Launcher was not in a configuration that could support loading.

    After standing down for a couple of days of rest, the third attempt was postponed when a gaseous helium check valve on the Interim Cryogenic Propulsion Stage (ICPS) used to fill pressure vessels on the SLS second stage stopped working. Following some maintenance of launch pad helium systems, the valve would no longer fully close to keep the helium in the stages pressure vessels.

    NASA decided to make the third attempt on April 14 without loading the ICPS with propellant or performing final launch preparations on the stage during terminal countdown. The GN2 supply again crashed during the third attempt, delaying the beginning of propellant loading, but the launch team was able to load LOX on the Core Stage and had started loading LH2 for the first time
    when a leak was detected in the hydrogen tail service mast umbilical (TSMU).

    The concentration of hydrogen gas around the umbilical lines spiked over the allowable 4% limit when LH2 loading transitioned from slow fill to fast fill. As a result, the hazardous gas violation automatically stopped the loading process, and it was decided to scrub the attempt.

    Following the scrub, the GN2 purge gas supply crashed for a second time on April 14 while the Core Stage was being drained. The second loss of purge
    flow was longer and more serious than the first. Following an assessment of the situation, NASA decided to roll back to VAB in late April to allow
    repairs and servicing to be performed on the rocket and launcher in parallel with repairs and upgrades necessary for Air Liquide to support future SLS tankings.

    Repair work and validation testing was mostly completed in May , leading to the second rollout to Pad 39B on June 6. Artemis 1 rollout on June 6. Credit: Julia Bergeron for NSF.

    NASA plans to complete the WDR test while the vehicle is out at the pad, including plans to possibly conduct a quick scrub turnaround exercise in preparation for another tanking by the end of the week. Once the agency is satisfied with the outcome of the test, the vehicle and Mobile Launcher will be prepared to roll back to the VAB where final pre-launch servicing and installations would be conducted before returning to the pad for launch.

    If the test goes well on June 20, one option would be to prepare the vehicle to roll back to the VAB as early as June 27, but that may depend on whether the scrub turnaround exercise is conducted and how long it lasts. In the meantime, NASA is not planning on officially targeting a launch date until after they can review results from a complete test.

    Depending on how cleanly the vehicle and ground systems come through the
    test, it may be possible for NASA to be ready to launch Artemis 1 by the end of the Summer, no earlier than a launch opportunity that opens in late August and runs through early September.

    Lead image credit: Julia Bergeron for NSF.

    The post NASA making fourth attempt to complete Artemis 1 Wet Dress Rehearsal appeared first on NASASpaceFlight.com .



    ======================================================================
    Link to news story:
    https://www.nasaspaceflight.com/2022/06/artemis-1-wdr-4/


    --- Mystic BBS v1.12 A47 (Linux/64)
    * Origin: tqwNet Science News (1337:1/100)