NASA moon rocket SLS ready for rollout to rebuilt LC-39B ahead of Artemis 1 rehearsal
Date:
Thu, 17 Mar 2022 17:34:40 +0000
Description:
A moment more than a decade in the making. NASAs Space Launch System (SLS) rocket The post NASA moon rocket SLS ready for rollout to rebuilt LC-39B
ahead of Artemis 1 rehearsal appeared first on NASASpaceFlight.com .
FULL STORY ======================================================================
A moment more than a decade in the making. NASAs Space Launch System (SLS) rocket for the Artemis 1 mission will make its first trip down the crawlerway at the Kennedy Space Center in Florida on Thursday evening, March 17.
Rollout first motion is currently scheduled for around 5:00 pm EDT (21:00 UTC) for a planned 11-hour journey to LC-39B. But when SLS arrives at the pad Friday morning, it will find a completely different, rebuilt launch complex from the previous vehicles that called it home.
The rollout marks a significant milestone for NASAs new Moon rocket that
will help ferry astronauts to lunar vicinity where they will then for
Artemis 3 transfer to a waiting SpaceX Starship lunar lander for humanitys planned return to the Moon later this decade.
Orion and SLS are also NASAs crew launch vehicles for missions to the upcoming Lunar Gateway station.
The rollout to Pad B will bring the 98.1 m (322 ft) tall rocket the 6.7 km (4.2 miles) from Vehicle Assembly Building (VAB) High Bay 3 (HB-3) to the pad for a series of pad connections, systems checkouts, and rocket integration work that will all lead to a full-up practice countdown complete with fueling and a countdown cutoff (stopping point) at just under the T-10 second mark.
But SLS will find a very different launch pad when it arrives than the one used by the final Shuttles and Ares I-X, the last rocket to launch from the pad in October 2009 .
Deeply rooted in history, Kennedy Space Centers Launch Complex 39B has been home to many transitions but none as major as the one for SLS. Once built to support the Saturn V and Apollo program , it transitioned to support the
Space Shuttle in the late-70s and early- to mid-80s, then a lasting change in the lightning towers for the now-canceled Constellation program, and now today, where it will once again support another Moon shot with the SLS and
the upcoming Artemis program.
Construction of 39B began in December 1964 and was completed nearly four years later in April 1967. While Launch Complex 39 A and B are near-identical builds, the only major difference between them is that Pad B sits 2.1 meters (7 feet) higher at 16.7 m (55 feet) above mean sea level.
The pad hosted a single human lunar orbit mission with Apollo 10 and Stafford, Young, and Cernan. It would be the first and only Saturn V mission launched from 39B when it lifted off on the programs everything-but-land rehearsal for the first Moon landing.
While 39A would support all of the human Moon landing missions, 39B would host the three crewed Skylab missions as well as the final launch of the Apollo program: the Apollo-Soyuz Test Project mission in July of 1975. The three lightning protection system towers at LC-39B. On the right side of the left-hand tower, you can see four weather stations sticking out to the side. Four more can be seen on the left side of the center tower. (Credit: Nathan Barker for NSF)
The clean pad was then abolished for the Shuttle Program, with a Fixed and Rotating Service Structure supporting Shuttle pad operations and fueling
needs . The pad also received hypergolic fuel and oxidizer lines as well as helium and nitrogen service lines.
Other significant modifications included the addition of an 88.3 m (290
foot) tall water tower to support the Sound Suppression System. Located on
the northeast side of the pad, this 300,000-gallon tank would release at T-16 seconds, with a peak flow rate of 900,000 gallons per minute.
A hydrogen flare stack was also added to the pad for the Shuttle era, even though the Saturn V before it had also used liquid hydrogen as a propellant. For Apollo, a hydrogen burn pond was used to eliminate this highly flammable fuel source.
But truly significant changes, a rebuild, was not possible until the Shuttle program ended and NASA could get into the pad which still had most of its 1960s technology and truly rebuild and modernize it. The SLS Block 1 Mobile Launcher at Pad B for testing. The water tower can be seen between the ML and a taller lightning protection system tower. (Credit: NASA)
The pad was built in the 60s, and since it was built, because of the amount of launches that we had in the Shuttle timeframe where the pad was basically operational seven days a week, 24 hours a day, there was little time to go
and do refurbishment or upgrades to the pad, said Jose Osvaldo Perez Morales, Senior Project Manager, Exploration Ground Systems about the changes to the pad and preparations to support SLS in an interview with NASASpaceflight.
Teams finally had a chance to truly rebuild Pad B and make it a 21st-century pad.
When I got the pad, first thing I had to do, obviously the cables that were serving Apollo and Shuttle were cables from the 1960s. The cables, the core was a big piece of copper.
And we decided to take every piece of cable out of the pad. We removed about 1.3 million feet of cable. Of which, at the time, I was fortunate enough to recycle that and buy all the fiber optic that I needed to install in the pad.
In all, the 1.3 million feet of copper cable was replaced with just 300,000 feet of fiber optic cable.
So we basically brought the pad to the 21st-century era, where now we are going to send messages through fiber instead of copper. And below the pads surface, theres a big room called the PTCR [Pad Terminal Connection Room].
And thats where all the electronics reside for launches. See Also Artemis 1 Updates SLS Forum Section L2 SLS Section Click here to Join L2
This is where all the systems that talk to all the valves and the different things that move the pad reside. Well, all that was taken out. We replaced that, obviously, with completely new electronics, with PLC [Programmable
Logic Controllers]-type controls, said Mr. Morales.
Back when I got to the pad, there were three or four rooms, I mean wall-to-wall, full of racks and electronics because obviously they were of
the 1960s era. Now, you go into the same room and you find three or four
racks and the room almost empty because youve got state-of-the-art PLCs that do the work of maybe 20 racks back in the Shuttle era.
Outside at the pad, the sound suppression system and flame trench were also completely reworked for SLS.
We did a tremendous amount of modifications to the ignition overpressure and sound suppression system to conform to the new vehicle, said Morales. Those pipes had been there since the 60s, and we brought them up. We basically modified the way the new mobile launcher was being fed from those pipes. The Core Stage for Artemis 1 during its arrival at the Kennedy Space Center in April 2021 with Pad-B behind it. (Credit: Nathan Barker for NSF)
Teams also refurbished the water tower, something that had never taken place before, and added numerous valves and systems for the dynamics the system
will have to withstand for SLS.
In the flame trench, all of the bricks from Apollo and Shuttle were removed and the pad structure inspected and refurbished before 96,000 new bricks were installed.
The trenchs flame deflector was also completely reworked. In the Shuttle
era, the deflector was lined with Fondu Fyre material and had to be refurbished between launches.
We took an idea of a flame deflector that they use in Guiana, said Morales. In Guiana, instead of using Fondu Fyre or any cement type area, what they
have is steel plate lining, like shingles on the roof of your house. Thats exactly what weve got now with this new flame deflector. Its about one inch, one and a half inch plates lining all the flame deflector.
It can take a lot more launches before you have to do any repairs, and it requires a lot less maintenance, noted Morales.
But a striking new addition to the pad from Apollo and Shuttle are three 600 foot lightning towers.
One of the first projects at the pad was to protect the vehicle from lightning strikes. The first concept had four towers, and we had this doctor from Venezuela who was an expert in lightning. And [there was a] theory called the Rolling Ball. And he did all kinds of models and basically came up with these three towers. The new Flame Deflector at 39B. (Credit:NASA/Kim Shiflett)
This theory proposed that with a three-tower design with nine conductors to the ground, the odds of having lightning strike any place in the area and not the towers was 1 in 10,000 years, according to Mr. Morales. And throughout
the years since 2011, we have never had a lightning strike go and basically hit the inside of the pad.
As part of the three-tower design, highspeed cameras were placed on the towers looking at the fiberglass lightning mast where lightning will strike.
We put some very high-speed cameras right before the fiberglass mast. Then
we put a bunch of sensors around the perimeter of the pad. Every time the potential energy from the air and the ground comes to a point, it triggers
the camera, saying, Hey, theres a possibility of lightning close by. And the cameras capture everything.
But the lightning protection towers at 39B also sport another upgrade that has never before been present: weather stations. 600-foot-tall lightning towers will help prevent lightning strikes at Launch Complex 39B during
future prelaunch and launch activities. Aerial footage shows workers
preparing the surface of one of the three lightning protection system towers for painting at @NASAKennedy . pic.twitter.com/x8OS7z010v
NASA's Exploration Ground Systems (@NASAGroundSys) August 6, 2019
Each lightning tower has four levels. Each level has a complete weather station. The closest weather station that the Launch Director had at the time during Shuttle, its about five miles away from the pad.
So they would have to make decisions on launch based on a weather station that was about five miles away from the pad. Now, theyre going to have these three towers, and each tower has four weather stations.
So youre going to have 12 weather stations all around your vehicle to basically understand what the exact conditions are for weather and make a decision if you can launch or not in a heartbeat.
While SLS wont need launch weather information for this trip to the pad, the weather stations will be critical for the multiple weeks of outdoor work and tests the vehicle will undergo for its Wet Dress Rehearsal campaign.
Of note, the electrical potential monitors will also play a key role in determining if the ground weather is acceptable to fuel the rocket and when work will have to stop at the pad for worker safety. The crawler transporter arrives at LC-39B with the SLS ML for pad testing in 2019. (Credit: Stephen Marr for NSF)
Presently, the Wet Dress Rehearsal is scheduled for April 3. This will involve a full fueling of the Core Stage built by Boeing and the Interim Cryogenic Propulsion Stage built by United Launch Alliance with liquid oxygen and liquid hydrogen and will give the Launch Team their first opportunity to take the vehicle through a near-full countdown.
After this, SLS will return to the VAB for final launch preparations before moving back to LC-39B for launch.
The currently No Earlier Than launch date for Artemis 1 is June 2022, with a formal target to be announced once the Wet Dress Rehearsal is complete.
(Lead image: Artists render of Artemis 1 at the launchpad. Credit: NASA)
The post NASA moon rocket SLS ready for rollout to rebuilt LC-39B ahead of Artemis 1 rehearsal appeared first on NASASpaceFlight.com .
======================================================================
Link to news story:
https://www.nasaspaceflight.com/2022/03/sls-rollout-wet-dress-rehearsal/